Lead Times for Custom Silicone Parts

Most late deliveries on custom silicone parts are not caused by slow production. They are caused by four specific stalls, all of which happen before the press starts.

The Schedule

StageTypical durationWhat has to be true to start
Drawing review and quotation1–3 working daysDrawing is dimensioned and states material and hardness
Tooling7–15 working daysQuotation accepted, tooling terms agreed
First sample2–3 working days after toolingTool is cut and trialled
Sample approval2–5 working daysBuyer measures and signs off
Production15–25 working daysSample approved, deposit received
Freight3–7 days air, 18–35 days seaBooking confirmed

Ready-made catalogue items skip the first four stages: 5–10 working days to dispatch from stock.

Stall One: The Drawing

A drawing without hardness, colour, tolerance or surface requirement cannot be quoted accurately, so it comes back with questions. Each round trip costs a day or two. The fix is a drawing that states material grade, hardness with test method, critical tolerances, surface finish and packaging.

Stall Two: Tooling Terms

Tooling invoiced separately, amortised into unit price, or credited at volume are three different commercial structures. Choosing one late delays the tool by however long the discussion takes. Decide at quotation, not after.

Stall Three: Sample Approval

The sample arrives, goes to the engineer, and sits on a desk. Two weeks later it is approved. Production has not started. This is the single most common cause of a late first order, and it is entirely inside the buyer's control. Book the inspection slot before the sample ships.

Stall Four: The Deposit

Production is scheduled on receipt of the deposit, not on approval of the sample. Where a purchase order and a payment run on different cycles, the gap shows up as a late delivery even though nobody was late.

What Actually Helps

  • Send the drawing with material, hardness and tolerances already on it.
  • Agree the tooling structure with the quotation.
  • Put the sample approval date in the purchase order.
  • Pay the deposit against the pro-forma invoice, not the purchase order.
  • For a fixed launch date, order the sample earlier than feels necessary and accept that the sample is a separate lead time.

A Realistic Total

From drawing to goods on a plane, plan on five to eight weeks for a new tooled part, and two to three weeks for a repeat order on existing tooling. Anything quoted well below that usually means a stage has been left out of the plan rather than compressed.